Tennessee Department of Transportation - TDOT

Nashville, TN – The Tennessee Department of Transportation (TDOT) in Montgomery County will be doing intersection improvements, grading, drainage, and construction of retaining walls on SR 112 / SR 76.

Daily from 9:00am until 3:00pm, there will be temporary lane closures for utility relocation, grading, and drainage installation (MM 9.19 – 9.41 and MM 14.1 – 14.2).

Montgomery County – SR 238

Pavement repair.
Daily, 9:00am – 3:00pm, there will be various lane closures along SR 238 for pavement repair (MM 0 – 8.25).

Montgomery County – SR 48

Sidewalk and crosswalk improvements.
Daily, 9:00am – 3:00pm, there will be temporary lane closures for replacing sidewalk along SR 48 (Trenton Road) at intersections between Needmore Road and Tiny Town Road (SR 236).

Montgomery County – SR 12

Sidewalk and crosswalk improvements.
Daily, 9:00am – 3:00pm, there will be temporary lane closures for replacing sidewalk along Riverside Drive (SR 12) intersections between Commerce Street to College Street.

Resurfacing on SR 12 from Hermitage Drive to the Kentucky state line.
4/21 – 4/23, 8:00pm – 5:00am, there will be alternating lane closures in both directions for thermoplastic placement and snowplowable markers installation (MM 19.75 – 23.78).

Davidson County – I-24

Resurfacing.
Nightly, 8:00pm – 5:00am, there will be alternating lane closures in both directions on I-24 near I-440 to near Haywood Lane to apply texture coating (MM 53 – 57).

Davidson County – I-40

TVA crossing replacement.
4/27, 6:00am – 9:00am, there will be a rolling roadblock to replace aerial crossing near MM 193.5.

Harpeth River bridge repair.
Nightly, 9:00pm – 5:00am, there will mobile operations in both directions on I-40 for roadway maintenance as needed (MM 194 – 196).

I-40/12th Avenue bridge repair.
Nightly, 9:00pm – 5:00am, there will be alternating lane closures on I-40 westbound under 12th Avenue for bridge construction. there will also be a lane closure on the I-40 westbound merge ramp to I-65 southbound for milling and paving.

Median cleaning on I-40 at MM 196 and working east.
Nightly, 8:00pm – 5:00am, Inside shoulder closure only.

Shoulder repair.
Daily, 9:00am – 4:00pm, there will be shoulder closures on I-40 westbound for shoulder repairs (MM 191.6 – 199).

Streetlight repair.
4/25, 1:00am – 5:00am, there will be an inside lane closure on I-40 eastbound at the I-65 underpass for streetlight repair. At the I-40 eastbound ramp to 4th Avenue South, the right lane of the exit ramp will be closed (MM 210 – 211).

Miscellaneous construction activities.
4/26, 9:00am – 4:00pm, there will be a lane closure at the ramps from Murfreesboro Pike to I-40 eastbound and I-40 westbound for vegetation removal and inlet cleaning. Both ramps will not be closed at the same time (MM 213).
 
Nashville International Airport/SR 255 over I-40 at the Donelson Pike Interchange.
Nightly, 8:00pm – 4:00am, there will be alternating double and triple right lane closures on I-40 in both directions for striping and removing the barrier walls (MM 214.4 – 218).

Davidson County – I-40 and I-440

Digital sign replacement.
LOOK AHEAD: 5/1, 8:00pm – 5:00am, there will be a double right lane closure on I-40 eastbound for digital messaging sign replacement (MM 205.2 – 207.2). there will also be rolling roadblocks in place.

LOOK AHEAD: 5/1 , 8:00pm – 5:00am, there will be a full closure on I-440 westbound at the ramp to I-40 eastbound for the digital messaging sign replacement. Detours will be in place.

Davidson County – I-65

Overhead sign installation.
Daily, 9:00am – 3:00pm, there will be daytime inside shoulder closures on I-65 northbound for overhead sign footing installation, temporary barrier wall installation, and guardrail installation (MM 79.8).

Pavement resurfacing.
Nightly, 8:00pm – 5:00am, there will be alternating lane closures in both directions on I-65 for milling, paving, and construction work from near Armory Drive to I-40 (MM 79 – 85).

Davidson County – I-440

Vegetation removal.
Daily, 9:00am– 4:00pm, there will be right shoulder closures to remove vegetation on the soundwalls of I-440 (MM 0 – 7.66). This operation will be mobile when possible.

Streetlight controller replacement.
Nightly, 8:00pm – 5:00am, there will be a single lane closure in both directions on I-440 for streetlighting controller replacements from Charlotte Avenue to Richardson Avenue (MM 0.4 – 1.8).

Nightly, 8:00pm – 5:00am, there will be a single lane closure in both direction on I-440 for streetlighting controller replacements from Granny White Pike to South Lyle Lane (MM 3.8 – 7.8).

Davidson County – SR 255

Nashville International Airport/SR 255 over I-40 at the Donelson Pike Interchange.
Daily, 9:00am – 3:00pm, there will be alternating lane closures on Donelson Pike for grading and utility work (MM 216).

Davidson County and Sumner County – I-65

I-65 widening and improvements from near Rivergate Parkway to near US 31W (SR 41).
Nightly, 8:00pm – 5:00am, there will be lane closures on I-65 in both directions for paving and construction work.

Nightly, 8:00pm – 5:00am, there will be temporary, intermittent ramp closures at Rivergate Parkway, Long Hollow Pike, and 31W for pavement work.

Dickson County – SR 46

The construction of a box beam bridge on SR 46 over Yellow Creek.
Daily, continuously, the bridge will be reduced to one lane in order to demo the existing structure and reconstruct the new bridge. Temporary signals will control traffic.

Hickman County – I-40

Fiber installation.
Nightly, 8:00pm – 6:00am, there will be temporary right lane closures in both directions on I-40 for fiber installation for the Intelligent Transportation System. One lane will always remain open (MM 148 – 150).

Humphreys County – I-40

The repair of bridges on I-40 over Squeeze Bottom Road and Buffalo River Bridge.
Nightly, 7:00pm – 5:00am, there will be temporary lane closures on I-40 in both directions for roadway maintenance as needed. One lane will always remain open (MM 140 – 142).

Robertson County – I-65

Sensor installation.
Nightly, 8:00pm – 5:00am, there will be lane closures in both directions on I-65 for Statewide Mainline Weigh-In Motion Program sensor installation (MM 118.1 – 120.6).

Robertson County – SR 76

Intersection improvements.
Daily, 8:00am – 3:00pm, there will be lane closures along SR 76 for grading, drainage, and pavement installation (MM 14.8 – 15.5).

Tennessee Department of Transportation

Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity. The contractors provide Information in this report to the Department of Transportation. Most work is weather-dependent and subject to change due to inclement weather.

For more information on this or any other TDOT road construction project or to view travel conditions in this area visit the TDOT SmartWay Information System website ( www.tn.gov/tdot/tdotsmartway/ ).

People can also dial 511 from any landline or cellular phone to access up-to-date traffic conditions, or visit www.TN511.com ( http://www.tn511.com/ ). TDOT is also now on Twitter. For up-to-date traffic tweets for the Nashville area follow Nashville511 ( http://twitter.com/nashville511 ) on Twitter. For statewide traffic tweets just follow TN511 ( http://twitter.com/TN511 ).

Motorists are reminded to use all motorist information tools responsibly. Drivers should refrain from texting, tweeting, or using a mobile phone while operating a vehicle.

RELATED ARTICLES

Latest Articles

Clarksville Online - Clarksville News, Sports, Events and Information