HomeNewsClarksville-Montgomery County area TDOT Work starting April 1st, 2024

Clarksville-Montgomery County area TDOT Work starting April 1st, 2024

Tennessee Department of Transportation - TDOT

Nashville, TN – The Tennessee Department of Transportation (TDOT) in Montgomery County will be resurfacing Interstate 24 from west of Trough Springs Road to Robertson County Line.

Nightly, from 8:00pm until 5:00am, there will be alternating lane closures EB and WB for milling and paving activities.

Montgomery County – SR 112 / SR 76

Intersection Improvements. Grading, drainage, and construction of Remaining walls.

Daily, 9:00am until 3:00pm, there will be temporary lane closures for utility relocation, grading and drainage installation.

Montgomery County – SR 48

The bridges on SR 48 over Bartons Creek (LM 0.40) and Louise Creek (LM 3.36) need to be repaired.

Continuous, the bridges will be reduced to one lane to demo and reconstruct the old bridge. Traffic will be controlled by temporary signals at each bridge.

Montgomery County – SR 149

The repair of the bridge on SR 149 over Yellow Creek (LM 1.53).

Continuous, the bridge will be reduced to one lane in order to demo and reconstruct the old bridge deck. Traffic will be controlled by temporary signals.

Davidson County – I-440

The on-call concrete pavement repair at various locations on various Interstate and State Routes

Nightly, 8:00pm – 6:00am, there will be alternating lane shifts at the I-440 EB ramp to Hillsboro and Hillsboro to I-440 EB ramp to saw damaged concrete. Ramps will remain open.

Davidson County – I-40

The repair of the bridges on I-65 over Arthur Avenue (LM 8.80) and the repair of the bridge on I-40 over I-40, I-65 and the I-65 ramp (LM 16.14).

Nightly, 8:00pm – 5:00am: Alternating lane closures on I-40 EB (Exit 208 B to I-65 N), and I-40 WB (Exit 208) for parapet and overhang demo on I65 interchange.

Look Ahead: 4/5 at 8:00pm continuously until 4/8 at 5:00am, there will be a full closure on I-40 Westbound at the flyover bridge from the downtown loop at MM 208/.02 Exit 208 for bridge repair. Traffic will be detoured via I440/Briley Parkway.

Look Ahead: 4/3 and 4/4, 8:00pm – 5:00am, The I-40E ramp to I-65N will be narrowed to one lane (8:00pm – 5:00am) and the I-40W ramp to I-65 will be closed (10:00pm – 5:00am) for Milling and paving.

The grading, drainage, construction of bridges, retaining walls and paving on I-40 (MM 216) at the Donelson Pike interchange.

Daily, 8:00pm – 4:00am, there will be alternating lane closures I-40 EB and WB for milling and paving operations.
 
Daily (excluding weekend), 1:00pm, there will be an alternating rolling roadblock on I-40 in both directions for blasting.

Davidson County – I-65

The repair of the bridges on I-65 over Arthur Avenue (LM 8.80) and the repair of the bridge on I-40 over I-40, I-65 and the I-65 ramp (LM 16.14).

Nightly, 8:00pm – 5:00am, there will be alternating lane closures on I-65 NB and SB for installation of beam strength plates and expansion joint repairs and parapet/overhang demo on I40 interchange.

Davidson County – SR 112

SR 112 (US 41A/Clarksville Pike) from SR 12 (Ashland City Highway) to SR 155 (Briley Parkway)

Daily, 9:00am – 3:00pm there will be temporary alternating lane closures on SR 112 Clarksville Pike in both directions for grade work, paving, water line work, storm drain installation and communications. The merging lane to Nashville on Ashland City Highway will be closed.

Dickson County / Williamson County / Cheatham County / Davidson County – I-40

The expansion of the SmartWay Intelligent Transportation System (ITS) on I-40 from near I-840 in Dickson County to near U.S. 70S (Exit 196) in Davidson County.

Daily 7:30am – 6:00pm, there will be temporary daytime shoulder closures in both directions for conduit installation at various locations throughout the project limits. (MM 174-196)

Nightly, 8:00pm – 5:00am, there will be temporary nighttime shoulder closures in both directions for conduit installation at various locations throughout the project limits. (MM 174-196)

Hickman County – I-40

The repair of the bridges on I-40 over Sugar Creek and Resurfacing on I-40.

Nightly, 7:00pm – 5:00am, there will be temporary lane closures on I-40 EB and WB for bridge repair work. One lane will remain open at all times.

Roberston County – I-65

Interstate Widening – Grading, drainage, construction of bridges and retaining walls, ITS and paving.

Nightly, 8:00pm – 5:00am, there will be temporary lane closures on I-65 NB and SB for roadway maintenance, One lane will remain open at all times.

Tennessee Department of Transportation

Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity. The contractors provide Information in this report to the Department of Transportation. Most work is weather-dependent and subject to change due to inclement weather.

For more information on this or any other TDOT road construction project or to view travel conditions in this area visit the TDOT SmartWay Information System website ( www.tn.gov/tdot/tdotsmartway/ ).

People can also dial 511 from any landline or cellular phone to access up-to-date traffic conditions, or visit www.TN511.com ( http://www.tn511.com/ ). TDOT is also now on Twitter. For up-to-date traffic tweets for the Nashville area follow Nashville511 ( http://twitter.com/nashville511 ) on Twitter. For statewide traffic tweets just follow TN511 ( http://twitter.com/TN511 ).

Motorists are reminded to use all motorist information tools responsibly. Drivers should refrain from texting, tweeting, or using a mobile phone while operating a vehicle.