Clarksville-Montgomery County area TDOT Work starting June 18th, 2023

Tennessee Department of Transportation (TDOT)

Tennessee Department of Transportation - TDOT

Nashville, TN – The Tennessee Department of Transportation (TDOT) in Montgomery County there will grading, drainage, construction of welded steel plate girder bridge, retaining wall, and paving on SR 149 and SR 13 from River Road to Zinc Plant Road.

Daily, 9:00am – 3:00pm, there will be temporary lane closures for final pavement at various locations throughout the project.

SR 112 / SR 76

Intersection Improvements on SR 112 / SR 76 to include grading, drainage, and construction of retaining walls.

Daily, 9:00am – 3:00pm, there will be temporary lane closures for utility relocation, grading, and drainage installation.

Davidson County

I-40

The resurfacing on I-40 from U.S. 70S (SR 1) (LM 4.71) to near U.S. 70 (SR 24, Charlotte Pike) (LM 9.61)

Nightly, 8:00pm – 5:00am, there will be multiple alternating lane and ramp closures for the installation of construction signs and degrassing operations.

The grading, drainage, construction of bridges, retaining walls and paving on I-40 (MM 216) at the Donelson Pike interchange

6/18 – 6/-21, 8:00pm – 4:00am, there will be lane closures on I-40 in both directions for paving operations.

I-440

The installation of an overhead sign structure on I-440 WB at the I-65 ramp (LM 5.2)

Daily, 9:00am – 3:00pm, there will be alternating shoulder closures on I-440 WB at Exit 5 to I-65 to begin foundation work (MM4.5)

I-65 / SR 254

The grading, drainage, construction of a retaining wall, signals, and paving on I-65 at the NB exit ramp to SR 254 (OHB, Exit 74A)

Daily, 9:00am – 3:00pm and 8:00pm – 5:00am, there will be temporary lane closures on SR 254 (OHB) in both directions for grading and signal work. Two lanes will remain open in each direction.

6/20, 9:00am – 3:00pm, there will be a ramp closure on I-65 NB to OHB WB to pour concrete.

SR 112

SR 112 (US 41A/Clarksville Pike) from SR 12 (Ashland City Highway) to SR 155 (Briley Parkway)

Daily, 9:00am – 3:00pm, there will be a temporary alternating lane closure on SR 112 Clarksville Pike in both directions for grade work, paving, installation of storm drainage, sanitary sewer, installation of water line, underground communications and overhead power. Courtney Avenue, Kings Lane, West Hamilton Lane and the merging lane to Nashville on Ashland City highway will be closed. Flaggers will be utilized.

Davidson County / Rutherford County

I-24

The installation of Smartway Intelligent Transportation System (ITS) on I-24 from I-440 to US-231

6/12 – 6/14, 8:00pm – 5:00am, there will be alternating lane closures EB and WB for guardrail installation.

Dickson County / Williamson County / Cheatham County / Davidson County

I-40

The expansion of the SmartWay Intelligent Transportation System (ITS) on I-40 from near I-840 in Dickson County to near U.S. 70S (Exit 196) in Davidson County

Daily, 7:30am – 6:00pm, there will be temporary daytime shoulder closure in both directions for trenching and boring operations at various locations throughout the project limits.

Nightly, 8:00pm – 5:00am, there will be temporary nighttime lane closure to remove guardrail, set barrier rail, and install an attenuator at each location listed.

  • MM 190-192
  • MM 191-193
  • MM 193-196
  • MM 192-196

Humphreys County / Hickman County

The resurfacing of I-40 in Humphreys County and Hickman County from MM 134.75 to MM 149.5

Nightly, 8:00pm – 5:00am, there will be temporary nighttime lane closures in both directions for paving operations. (MM 135 – 141)

Looking Ahead: 6/23 – 6/26 & 7/7 – 7/10, continuously from 7:00pm Friday until 5:00am Monday, there will be continuous weekend closures for bridge deck repairs and expansion joint replacements in both directions.

Robertson County

I-65

Interstate Widening – Grading, drainage, construction of bridges and retaining walls, ITS and paving

Nightly, 8:00pm – 5:00am there will be temporary lane closures on I-65 NB and SB for roadway maintenance, one lane will always remain open.

Scheduled Maintenance Work

Davidson County – I-24

Mill and Fill as Needed

Daily, 9:00am – 3:00pm, Various lane closures and shoulder closed as needed (MM 32-63).

Davidson County – I-24

Slope Mowing

6/17, 6:00am – noon, EB Exit 53 ramp to I-440 West will be closed for mowing activities.

Davidson County – I-40

Mill and fill as needed

Nightly, 8:00pm – 5:00am, One EB lane closed for milling and paving. (MM 192 – 193)

Tennessee Department of Transportation

Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity. Information in this report is provided to the Department of Transportation by the contractors. Most work is weather-dependent and subject to change due to inclement weather.

For more information on this or any other TDOT road construction project or to view travel conditions in this area visit the TDOT SmartWay Information System website ( www.tn.gov/tdot/tdotsmartway/ ).

People can also dial 511 from any landline or cellular phone to access up-to-date traffic conditions, or visit www.TN511.com ( http://www.tn511.com/ ). TDOT is also now on Twitter. For up-to-date traffic tweets for the Nashville area follow Nashville511 ( http://twitter.com/nashville511 ) on Twitter. For statewide traffic tweets just follow TN511 ( http://twitter.com/TN511 ).

Motorists are reminded to use all motorist information tools responsibly. Drivers should refrain from texting, tweeting, or using a mobile phone while operating a vehicle.

­